Cora allows the user to create different types of links between tasks in the Gantt chart.
- Click ADD
The most common type of link is a Finish to Start (FS) link.
Cora supports all the common predecessors:
- FS Finish-to-Start
- SS Start-to-Start
- FF Finish-to-Finish
- SF Start-to-Finish
Elapsed time is used when the lag duration includes non-working days.
Set the predecessor to make the start date of a task dependent on the end date of one or more tasks.
You can also do this by dragging one task onto another in the Gantt.
The predecessors of a particular task can be viewed in the predecessor column and can also be edited and changed there.