Admin - IPMDAR

Modified on Mon, 28 Sep at 3:13 PM

GovCon: IPMDAR

Integrated Program Management Data and Analysis Report (IPMDAR) transforms project oversight from a retrospective reporting exercise into a proactive decision-making engine. By providing a standardized, high-fidelity data exchange between the contractor and the government, IPMDAR enables real-time visibility into the relationship between cost, schedule, and technical performance. This transparency reduces administrative burden, eliminates data silos, and empowers leadership to identify risks and execute corrective actions before they impact the mission.


content.emoticon.pin Toggles

Note: All required toggles for EVM, including Baselines, Traceability Registers and Rate Matrix, are listed below. Given they are required to generate EVM, they are also needed for IPMDAR.

Feature Toggle(s)

Permanent Toggle(s)

EVM

 144924_Set_EV_Percent_Complete_to_100

 

Baselines

 100008_Financial_Baseline_Comparison_MVP
107588_C2_Task_Changes_to_Support_Baseline_Change_
71407_Baseline_Financial_Comparisions_Design_New_M

 Updated_Baselines
BaselineChangeControl

Rate Matrix

 114927_Add_Filter_functionality_to_Rate_Matrix_Gri
67343_RateMatrix
84471_Burden_Costs_Calculations
90057_Ability_to_include_Wildcard_in_Rate_Matrix_A
134906_Adjust_Rate_Matrix_for_Baseline
126223_Add_Filter_Functionality_to_Burden_Matrix_G
130498_Show_AFinFMW
91810_Enterprise_Financials_Support_13_Periods

 

Schedule

141598_Hide_Expected_Date_on_Materials
121094_Statusing_25_Distribute_ETC_from_Status_Da
104235_Ability_to_view_on_OOB_Forecast_screen_in_a
105269_Scheduling_Free_Float_Field_and_Calculation
111141_New_Cost_columns_in_the_GanttSchedule
67077_StatusDate_Configuration_Setting
70822_Ability_to_clear_Forecast_as_of_the_Status_D

KanbanBoard
DuplicateSkillsOnTasks
TASKFMSLINK
TMActualPopup

EVM

 144924_Set_EV_Percent_Complete_to_100

 

Traceability Registers

AlternativeHierarchies

?️ Configuration (Admin)

  • Administration > System > My Installation > Features

    • Ensure GovCon is checked and click Update

      image-20250620-144538.png
  • Administration > Configuration > Project Toolbar

    • Add IPMDAR Configuration directly to tool bar or tool bar group.

 

? Items to be aware of (Gotchas)

Item

Admin, End User, or Both

 The Status Date is set

  • A current, active, and approved baseline exists for:

    • PMB (Performance Measurement Baseline)

    • MTH (Month End Baseline)

    • EAC (Estimate at Completion Baseline)

 End User

IPMDAR can only be run for the current period. Once the new period data is generated, prior periods will not be available.

End User

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article