GovCon: EAC Analysis
An EAC analysis—Estimate at Completion analysis—is a project management technique used to forecast the total expected cost of a project based on current performance.
Toggles
Note: To use EVM in Cora, you must enable both the Baseline and Rate Matrix functionality, as EVM cannot function properly without them. All required toggles for EVM, including Baselines and Rate Matrix, are listed below.
Feature Toggle(s) | Permanent Toggle(s) |
EVM | |
144924_Set_EV_Percent_Complete_to_100 |
|
Baselines | |
100008_Financial_Baseline_Comparison_MVP | Updated_Baselines |
Rate Matrix | |
114927_Add_Filter_functionality_to_Rate_Matrix_Gri |
|
Schedule | |
141598_Hide_Expected_Date_on_Materials | KanbanBoard |
?️ Configuration (Admin)
Administration > System > My Installation > Features
Ensure GovCon is checked and click Update
Administration > Configuration > Project Profiles
Select #55 EAC Analysis - User can view EAC Analysis page to any profiles that will need to view this information.
Administration > Configuration > Project Toolbar
Add EAC Analysis directly to tool bar or tool bar group.
? Items to be aware of (Gotchas)
Item | Admin, End User, or Both |
|---|---|
The Status Date is set
| End User |
EAC Analysis data can only be generated for the current period. If a prior period was not generated, the system cannot go back and generate. | End User |
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article