Adding Skills to a task is the first step in Resource Management.
To add a skill:
- Click Add
- Pick a skill from the drop-down menu
- Choose how the effort is to be measured
- Set the effort required
- Set the Distribution
- Set the Account Code
- Set the Rate Adjustment.
Note: The Rate Matrix integrates at both project and task levels, allowing for specific cost attribution to individual tasks based on their unique attributes.
- Click Add
You can remove a skill by clicking on the red bin icon beside it:
Once a Skill(s) has been attached to a task, an orange star icon will appear in the Info column alongside the task on the Gantt and on the task in the WBS to identify a Skill has been allocated: