The company calendar is where administrators set non-working days, such as weekends and national holidays. This is done within the initial configuration.
If a task’s starting date is on a Thursday and it has a duration of 3 days and the following Monday has been set as a non-working day, the task’s completion date will be set to the Tuesday. The duration remains the same but the extra non-working day is skipped.