GovCon: Contract Budget Log (CBL)
The Contract Budget Log aligns the financial model around CLIN records and improving system-driven synchronization between scheduling, budgeting, and the CBL, this feature enhances auditability, enforces data integrity, reduces manual effort, and improves compliance with earned value management (EVM) best practices. It provides stakeholders with a reliable and automated way to trace budget impacts from planning through approval and change management.
Toggles
Note: To use CBL in Cora, you must enable both the Traceability Registers and Baseline Change Controls functionality, as CBL cannot function properly without them. All required toggles for CBL, including Baselines and Registers, are listed below.
Feature Toggle(s) | Permanent Toggle(s) |
EVM |
|
144924_Set_EV_Percent_Complete_to_100 |
|
Baselines |
|
100008_Financial_Baseline_Comparison_MVP | Updated_Baselines |
Rate Matrix |
|
114927_Add_Filter_functionality_to_Rate_Matrix_Gri |
|
Schedule |
|
141598_Hide_Expected_Date_on_Materials | KanbanBoard |
Traceability Registers | |
AlternativeHierarchies | |
Contract Management | |
Contract_Management |
?️ Configuration (Admin)
Administration > System > My Installation > Features
Ensure GovCon is checked and click Update
Administration > Configuration > Project Toolbar
Add Contract Budget Log (item) directly to tool bar or tool bar group.
? Items to be aware of (Gotchas!)
Item | Admin, End User, or Both |
|---|---|
Contract Budget Log references the WBS & Contract (CLIN) Register and Baseline Change Control Register therefore all are required. | Both |
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article